Understanding Project Health

The project health feature provides automated analysis of your project’s progress compared to its timeline.

The health dashboard shows:

  • Timeline Progress - How much time has elapsed since the project started
  • Task Progress - Percentage of tasks completed
  • Variance - The difference between task progress and timeline progress
VarianceStatusMeaning
> +5%AheadTasks are ahead of schedule
-5% to +5%On TrackProject is progressing as expected
-5% to -20%BehindTasks are falling behind the timeline
< -20%CriticalSignificant delay, attention needed

Based on the calculated variance, the system may suggest updating your project status:

  • On Track - Progress matches or exceeds timeline
  • At Risk - Minor delays detected
  • Needs Attention - Significant delays require action

Health metrics require:

  • A start date for the project
  • A due date for the project
  • At least one task in the project

If any of these are missing, the health analysis cannot be performed.

If the suggested status differs from the current status, you can update it directly from this drawer by clicking the “Update Status” button.